Date de publication: 13 juin 2008
Promoteur – Intermédiaire Financier
Vodokanal of St PetersburgLieu
Description
The project concerns an investment programme encompassing: (i) completion of the Northern Tunnel Collector (NTC); (ii) pumping station and buildings; (iii) connection of current direct discharges of untreated wastewater; (iv) reconstruction of Central and Northern wastewater treatment plants.
It is a project within the framework of the Northern Dimension Environmental Partnership (NDEP).
Objectifs
The project objective is to eliminate discharges of untreated wastewater into the river Neva and enhance wastewater treatment.
Secteur(s)
Montant BEI envisagé (montant approximatif)
EUR 17.5 million.
Coût total (montant approximatif)
Approximately EUR 560 million.
Aspects environnementaux
Through the proposed investment programme, the load of nitrogen and phosphorous to the Gulf of Finland / Baltic Sea is expected to be reduced considerably. The implementation of the proposed programme will promote the fulfilment of the commitments made under the HELCOM convention. As a result the City of St Petersburg will comply with the EU recommendations of 94% efficiency in wastewater treatment.
Passation des marchés
Goods, works and services financed under the Bank's loan will be procured by open tendering procedures.
Statut
Signé - 4/06/2009
Clause de non-responsabilité
Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).