Date de publication: 22 juillet 2003
Promoteur – Intermédiaire Financier
Tunisacier S.A., part of the Riva GroupLieu
Description
The project involves the modernisation and expansion of an existing metallurgical plant, currently producing galvanised steel sheets, to transform it into a rolling and coated steel production centre, fully integrated with the parent’s Group’s overall upstream and downstream operations.
Objectifs
The objective is to enlarge the product range of the mill, enabling it to produce a much broader variety of cold-coated coils.
Commentaires
Steel.
Secteur(s)
Montant BEI envisagé (montant approximatif)
EUR 35 million
Coût total (montant approximatif)
EUR 75 million
Aspects environnementaux
Studies on the impact of each element of of the project, as well as appropriate mitigating measures are presented to the competent Tunisian Authorities (Agence Nationale pour l’Environnement) and are approved individually. The project is expected to have relatively little environmental impact.
Passation des marchés
Usual procedure of international consultation with a few specialised engineering companies. This procedure, usual in this industry, is in the best interest of the project and in line with the Bank’s procurement policy for private industry projects.
Statut
Signé - 9/10/2003
Clause de non-responsabilité
Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).