DARS, Druzba za avtoceste v Republiki Sloveniji d.d., Celje, a joint-stock company 100 percent owned by the Republic of SloveniaLieu
Description
The project consists of the motorway construction with total lenght of some 37 km. The works are located in 4 sections along the Slovenian North-South road corridor between Setvid and the Croatian border.
Objectifs
To increase traffic efficiency from Austria and Italy towards Zagreb and Belgrade, and further to Bulgaria and Greece. The proposed investments form part of Priority Corridor No. X of the Pan-European Road Network for Central and Eastern Europe.
Commentaires
Motorways
Secteur(s)
Montant BEI envisagé (montant approximatif)
Loan of up to EUR 120 million
Coût total (montant approximatif)
EUR 320 million
Aspects environnementaux
All 4 sections require a full Environmental Impact Assessment, all 4 have been completed.
Passation des marchés
All the contracts to be financed by the Bank will be advertised in the EU Official Journal and open on equal terms to international competition in accordance with the Bank's procurement criteria.
Statut
Signé - 27/12/2002
Clause de non-responsabilité
Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).