    The project comprises the construction of a 90 MW offshore wind farm in the East Irish Sea near Barrow-in-Furness. The wind farm is expected to produce 305 GWh annually, which is equivalent to supplying more than 65,000 households with renewable energy.

    Objectifs

    The project aims at providing renewable energy to the public network. It forms an important part of the UK Government’s attempt to increase the share of UK electricity generation from renewable sources to 10% by 2010 with the aim of combating climate change.

    Commentaires

    Environment and Climate Change.

    Secteur(s)

    Montant BEI envisagé (montant approximatif)

    Up to GBP 60 million.

    Coût total (montant approximatif)

    Estimated to be about GBP 123 million.

    Aspects environnementaux

    The project falls under Annex II of the Environmental Impact Assessment (EIA) Directive (85/337/EEC as amended by 97/11/EC). Planning permission was granted to the project on the basis of the EIA carried out by Warwick Energy in May 2002. Environmental issues in addition to the EIA are being surveyed both before construction, under construction and post-completion. The results will be reported annually to the authorities. The monitoring system also ensures that the project complies with the EU Nature Protection Directives and does not have a significant negative effect on any site of nature conservation importance, including Natura 2000 listed sites. The promoter will be required to provide copies of the non-technical summaries of the EIA and to implement any recommended mitigating measures to the satisfaction of the Bank.

    Passation des marchés

    The project will be implemented under a fixed lump sum EPC contract that was tendered after advertising in the OJEC in 2004. The promoters have confirmed that the procurement procedures followed comply with the requirements of EU directive 93/38.

    Statut

    Signé - 20/12/2005

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

    Mots-clés correspondants

    Royaume-Uni Énergie