Date de publication: 19 décembre 2002
Promoteur – Intermédiaire Financier
BCIE (Banco Centroamericano de Integracion Economica)Lieu
Description
The main components are a 1,830 km circuit overhead transmission line with fibre optic cable and the extension of 16 existing substations, including reactive compensation equipment.
Objectifs
The project aims at integrating the high-voltage power transmission systems of the six participating countries in Central America (Panama, Costa Rica, Nicaragua, Honduras, El Salvador and Guatemala), with the objective to form a regional electricity market and to provide mutual support in order to promote the least cost development of power generation in the region.
Secteur(s)
Montant BEI envisagé (montant approximatif)
EUR 35.6 million
Coût total (montant approximatif)
EUR 390.7 million
Aspects environnementaux
The project will be designed to comply with the environmental regulations of the countries concerned.
Passation des marchés
The components financed by the Bank will follow open procurement procedures with publication in the Official Journal of the European Communities.
Statut
Signé - 13/05/2003