Recherche Fr menu fr ClientConnect
Recherche
Résultats
5 premiers résultats de la recherche Voir tous les résultats Recherche avancée
Recherches les plus fréquentes
Pages les plus visitées

    Fiche récapitulative

    Date de publication
    19 octobre 2021
    Statut
    Référence
    Approuvé | 10/12/2021
    20210537
    Nom du projet
    Promoteur – Intermédiaire financier
    RECONSTRUCTION OF CHAIN BRIDGE (FL20140173)
    BUDAPEST FOVAROS ONKORMANYZATA
    Montant BEI envisagé (montant approximatif)
    Coût total (montant approximatif)
    EUR 58 million
    EUR 78 million
    Lieu
    Secteur(s)
    Description
    Objectifs

    Comprehensive reconstruction of the Széchenyi Chain Bridge in Budapest which is a historic landmark of the city.

    The project consists of the rehabilitation of the Széchenyi Chain Bridge in Budapest, a historical monument part of the national cultural heritage, located in the centre of the city (classified as part of the World Heritage) connecting the two sides of the city over the Danube. The status of the bridge and its related structures are deteriorated, so their reconstruction has become indispensable. The project's objective is to preserve the bridge's functionality as well as to improve the level of service for sustainable transport modes (public and non-motorised transport).

    Additionality and Impact

    The project consists of the rehabilitation of the Chain Bridge in Budapest. The status of the bridge and its related structures are deteriorated, so their reconstruction has become indispensable. The reconstruction will improve the connectivity and the travel conditions (in terms of efficiency, safety and comfort) between Buda and Pest in the heart of the city center. By reconstituting bridge's functionality, the project would also lead to an improvement of the level of service for the public transport as well as non-motorised transport users.

     

    The project will maintain and even improve accessibility, addressing market failures related to barriers to access transport options (accessible transport). It will also address market failures related to road externalities in terms of road safety (safe transport) as well as air, noise pollution and GHG emissions (green transport) through an improvement of the level of service for the sustainable transport modes (public and non-motorised transport). The project is fully in line with EU and EIB objectives on sustainable cities and regions, climate action and environmental sustainability.

     

    The project is expected to provide good socio economic benefits mainly in terms of better travel times for all users and lower operational costs for public transport operators, due to improved traffic conditions as well as drastically reduced maintenance costs for the city, thanks to the reconstruction. Further benefits may occur from the possible modal shift, through the improvement of the level of service for sustainable transport modes and the consequent reduction of road externalities (congestion, accidents, air and noise pollution and GHG emissions). Finally, the reconstruction will

    preserve the identity of the bridge as a World Heritage Site, an outstanding symbolic value for the City.

     

    EIB, through its technical and financial contribution, will support the implementation of a vital priority urban transport project for the city that is also included in the Transport Development and Investment Programme of the Budapest Mobility Plan.

    Aspects environnementaux
    Passation des marchés

    The project is included in the Budapest Mobility Plan (BMT) that was subject to a Strategic Environmental Assessment (SEA), approved in 2019. The scope of the project is a protected UNESCO World Heritage site. The project has not been classified under Annex I or Annex II of the Directive 2014/52/EU amending the EIA Directive 2011/92/EU by the Pest County Governmental Office, Environmental Protection and Nature Protection Department. This has been confirmed by a statement from the competent authority issued in 2016. Compliance with environmental legislation will be verified during appraisal, notably for environmental impacts, as well as nature and world heritage conservations aspects.

    The Bank will require the Promoter to ensure that contracts for implementation of the project have been tendered in accordance with the applicable EU procurement legislation, Directive 2014/24/EU as well as Directive 89/665/EEC as interpreted by the Court of Justice of the EU, with publication of tender notices in the Official Journal of the EU, as and where required. The public procurement process will be further analysed during appraisal.

    Projets associés
    Projet apparenté
    Lien vers la source

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

    Documents

    Fiche technique sur les aspects sociaux et environnementaux - RECONSTRUCTION OF CHAIN BRIDGE (FL20140173)
    Date de publication
    15 déc. 2021
    Langue
    Sujet général
    Prêts
    Numéro du document
    149693488
    Thématique du document
    Information Environnementale
    Numéro du projet
    20210537
    Secteur(s)
    Pays
    Disponible au public
    Télécharger maintenant
    Autres liens

    Informations et observations générales

    La BEI s’engage à communiquer de manière ouverte et encourage les parties prenantes à apporter des contributions constructives à ses activités.
    Les demandes ou observations concernant la participation de la BEI à des projets ou à des mécanismes de financement, ou concernant les activités, l’organisation et les objectifs de la BEI, peuvent être adressées à l’Infodesk de la BEI.
    Vous pouvez aussi prendre contact avec la BEI par l’intermédiaire de ses bureaux extérieurs.
    Veuillez, de préférence, adresser directement au promoteur du projet vos questions portant sur les détails d’un projet précis, notamment lorsque celui-ci fait l’objet d’une instruction de la BEI.

    Informations aux médias

    Les questions liées aux médias peuvent être adressées au service de presse de la BEI. Veuillez consulter également notre espace presse.

    Mécanisme de traitement des plaintes

    Toute plainte relative à une présomption de mauvaise administration peut être introduite auprès du Mécanisme de traitement des plaintes de la BEI. Le Médiateur européen agit en tant que mécanisme de recours indépendant externe à la BEI.

    Tolérance zéro face à la fraude et à la corruption

    La BEI pratique une politique de tolérance zéro face à la fraude et à la corruption. Pour signaler des allégations de fraude et de corruption en rapport avec des projets financés par la BEI, veuillez contacter la division Enquêtes sur les fraudes. Toutes les plaintes seront traitées de manière strictement confidentielle et selon les procedures d'investigation de la BEI et la politique antifraude.

    Publications connexes