Date de publication: 3 septembre 2010
Promoteur – Intermédiaire Financier
Private company
Lieu
Description
The project consists in a combined cycle gas turbine (CCGT) power station with an electric capacity of 400 MWe and heating capacity of 240 MWth.
Objectifs
The unit will provide electricity to the grid and heat to the neighbouring towns.
Secteur(s)
Montant BEI envisagé (montant approximatif)
EUR 162 million.
Coût total (montant approximatif)
EUR 400 million.
Aspects environnementaux
Due to its capacity (plant over 300 MWth), the project is subject to the Annex I of the EIA Directive (85/337/EC and amendments) and was required to undergo a full Environmental Impact Assessment. The EIA is completed and the environmental permit was granted by the competent authorities.
Passation des marchés
The main project contractor will be chosen based on Public Procurement Law through negotiations with publication. The procedure will comply with the EU Directive 2004/17/EC.
Statut
Signé - 21/12/2012