Date de publication: 16 novembre 2001
Promoteur – Intermédiaire Financier
Bahia de Bizkaia Gas SL (BBG)Lieu
Description
The project concerns the design, construction and operation of a LNG (Liquefied Natural Gas) import terminal towards the western extremity of the Bay of Vizcaya, which harbours the port of Bilbao (Basque country).
Objectifs
The project will contribute to meeting gas demand growth, and diversifying gas imports to the Iberian Peninsula. The LNG terminal will receive LNG shipments and deliver natural gas to both the adjacent power plant and the regional/national gas transmission grids.
Commentaires
LNG (Liquefied Natural Gas).
Secteur(s)
Montant BEI envisagé (montant approximatif)
Up to 75% of project cost.
Coût total (montant approximatif)
Approximately EUR 270 M.
Aspects environnementaux
The LNG terminal comes under Annex I of the Environmental Impact Assessment Directive 97/11/EC. The promoters have conducted a formal EIA including public consultation, and have obtained conditional approval from the Ministry of Environment in November 2000 (“Declaración de Impacto Ambiental”).
Passation des marchés
In accordance with directive 93/38/EC, the promoter has advertised for a range of materials in the EC Official Journal.
Statut
Signé - 3/03/2003