Cimpor Yibitas Ankara Clinker Plant
Cimpor Inversiones, S.A.
Montant BEI envisagé (montant approximatif)
Coût total (montant approximatif)
Up to EUR 50 million.
EUR 120 million.
Description
Objectifs
Construction of a clinker line at an existing grinding plant.
Reduce costs due to the replacement of clinker bought from third parties, strengthen Turkey’s industrial base, and stimulate economic development.
Aspects environnementaux
Passation des marchés
The project would fall under Annex II of 97/11 Directive amended by 2003/35, which leaves the determination on the EIA to national legislation. Based on preliminary EIA studies, the Public Authority decided that a full EIA is not required due to the location within an existing industrial zone and atmospheric emissions of new production to be in line with EU standards.
EU procurement legislation would not apply to this private sector project even if the project were located .in the EU.