The project concerns the construction of an 826 MW natural gas fired combined cycle gas-turbine (CCGT) at Agios Nikolaos, Viotias, Greece.

Ziele

The new CCGT power plant will have a nominal capacity of 826MW.

Sektor(en)

Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

EUR 125 million

Gesamtkosten (voraussichtlicher Betrag)

EUR 322 million

Umweltaspekte

An Environmental Impact Assessment (EIA) has been completed for the plant and the Environmental Permits have been approved by the Competent Authorities. The promoter has indicated that no E&S issues or concerns have arisen during public consultation period. Emissions from the plant will be in line with the relevant EU directive requirements.

Auftragsvergabe

The promoter is an operator in the private sector in the sense of the EIB's Guide to Procurement. The project will be implemented by the promoter's Engineering, Procurement, Construction (EPC) business unit. The main equipment supply has been competitively tendered and has been awarded to a leading equipment supplier.

Projektstatus

Unterzeichnet - 21/07/2020