Référence:
20150575
Date de publication: 14 mars 2016
Date de publication: 14 mars 2016
Promoteur – Intermédiaire Financier
FINA ENERJI HOLDING ASLieu
Description
Construction of three wind-power plants in Turkey (Uluborlu, Kizilcaterzi and Karova) for a total capacity of 106MW, together with associated facilities, power substations and interconnection lines
Objectifs
Generation of electricity from onshore wind farms
Secteur(s)
- Énergie - Production et distribution d'électricité, de gaz, de vapeur et d'air conditionné
Montant BEI envisagé (montant approximatif)
EUR 50 million
Coût total (montant approximatif)
EUR 131 million
Aspects environnementaux
The Bank will review the environmental and social assessments and corresponding authorisation processes during appraisal, including a verification of compliance with its environmental and social standards.
Passation des marchés
The Bank will require the promoter to ensure that any procurement procedures are done in accordance with the Bank's Guide to Procurement.
Statut
Signé - 28/10/2016