Date de publication: 25 octobre 2007
Promoteur – Intermédiaire Financier
Glas Cymru Cyfyngedig (Welsh Water)Lieu
Description
The project comprises Welsh Water’s capital programme for the 2005-10 period, which is approved and monitored by the industry regulator OFWAT. The project consists of a large number of water supply and wastewater schemes located throughout Welsh Water’s operating area.
Objectifs
The proposed programme aims to support sustainable environmental and customer service standards set by EU and national legislation.
Secteur(s)
Montant BEI envisagé (montant approximatif)
GBP 100 million.
Coût total (montant approximatif)
Estimated to be about GBP 566 million.
Aspects environnementaux
The schemes included in the project fall under Annex II of Directive 97/11/EC. Environmental Impact Assessment (EIA) procedures are carried out where required by the competent authorities and mitigating measures are applied as appropriate. The project will be compliant with Article 6 of the Habitats Directive 92/43/EEC.
Passation des marchés
The project falls under the EU Procurement Directive 2004/17/EC and 2004/18/EC. The borrower has confirmed that it complies fully with the requirements of the Procurement Directive and its amendment.
Statut
Signé - 23/10/2008