Référence: 20010499
Date de publication: 13 mars 2002

Promoteur – Intermédiaire Financier

Office National de l'Electricité (ONE)

Lieu

Description

  • Construction of a second submarine interconnection between Morocco and Spain;
  • Construction of a first 400 kV trunk line between Melloussa (North) and Médiouna (Centre) and a second 400 kV trunk line towards the East and Algeria;
  • Upgrading and extension of 225 kV and 60 kV networks in northern and central Morocco.

Objectifs

The aim of the project is to increase the transmission capacity of power interconnections between Morocco and two of its neighbours, Spain and Algeria, and to enhance the security and reliability of the existing national network.

Commentaires

Electricity

Secteur(s)

Montant BEI envisagé (montant approximatif)

EUR 120 mio

Coût total (montant approximatif)

MAD 3 105 mio (EUR 310 mio)

Aspects environnementaux

An Environmental Impact Assessment (EIA) of the project is under way.

Passation des marchés

Contracts for the project's various components will be subject to international competitive bidding with publication in the Official Journal of the European Communities (OJEC).

Statut

Signé - 16/10/2002

Clause de non-responsabilité

Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

Mots-clés correspondants

Maroc Énergie