Lien vers la source
Fiche technique
Autres liens
Fiche récapitulative
Date de publication
1 octobre 2003
Statut
Référence
Signé | 18/12/2003
20030307
Nom du projet
Promoteur – Intermédiaire financier
EDA Power VI
Electricidade dos Açores – EDA SA
Montant BEI envisagé (montant approximatif)
Coût total (montant approximatif)
Up to 50% of total project cost
Estimated at EUR 145 million
Description
Objectifs
Design and implementation of additional electricity generation, transmission and distribution capacity. The investments will be located in all nine of the islands making up the Archipelago of the Açores.
To meet the expected increase in electricity demand through appropriate increases in plant capacity and strengthening of transmission and distribution networks.
Aspects environnementaux
Passation des marchés
The project falls under Annex II of EC Directive 97/11, which will be complied with in full. The project will have a positive effect on the environment through use of efficient generation plant and enhanced use of renewable energy resources.
Procurement procedures are in compliance with relevant EU directives and national and regional legislation.
Lien vers la source
Fiche récapitulative
Autres liens
Fiche technique