The project consists of a 3-year investment programme (2009-2011) aimed at reinforcing and extending the promoter's transmission and distribution electricity networks throughout Estonia.
Objectifs
The main purpose of the project is to cater for demand growth, to improve quality and reliability of electricity supply and to support the connection and the efficient exploitation of renewable generation resources.
Secteur(s)
Montant BEI envisagé (montant approximatif)
EUR 150 million.
Coût total (montant approximatif)
The project cost is estimated to be EUR 410 million, EUR 300 million for distribution and EUR 110 million for transmission.
Aspects environnementaux
Some schemes will fall under Annex I of the EIA Directive while the remainder will fall under ANNEX II, leaving it to the national competent authority to decide whether an EIA would be required in line with the screening criteria specified in the directive.
Passation des marchés
The promoter is subject to the Public Procurement Act of Estonia that came into force in May 2007 transposing the EU Directives on public procurement.
Statut
Signé - 25/05/2009
Clause de non-responsabilité
Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).