Date de publication: 18 septembre 2008
Promoteur – Intermédiaire Financier
OGK-5 JSCContact person: Mr Luca Sutera, OGK-5 Chief Financial Officer
Lieu
Description
Upgrade of the Nevinnomyssk GRES power plant in Southern Russia, including the rehabilitation of existing generating capacity and building of a modern, efficient Combined Cycle Gas Turbine (CCGT) unit to replace two old gas-fired steam units.
Objectifs
The project aims to increase energy efficiency and to promote the differentiation of energy supply as well as operational safety of the energy infrastructure.
Secteur(s)
Montant BEI envisagé (montant approximatif)
Up to EUR 250 million.
Coût total (montant approximatif)
Approximately EUR 500 million (including construction of the CCGT as well as rehabilitation of existing generating capacity).
Aspects environnementaux
Due to its size and technical characteristics, the project requires an Environmental Impact Assessment (EIA) under EIB guidelines. The EIA process has been initiated and its review will form part of the Bank's appraisal of the project. The project is expected to contribute to meeting growing electricity demand with a lower environmental impact than other fossil fuel based alternatives.
Passation des marchés
The rehabilitation component of the project is expected to be procured under a number of separate works, supply and services contracts using mainly international tendering procedures. The new CCGT plant will be procured under a single Engineering, Procurement and Construction (EPC) contract. CCGT plant procurement has been initiated by OGK-5 under RAO UES public procurement practices, and the procurement has been completed after privatisation of the company.
Statut
Signé - 26/03/2010
Clause de non-responsabilité
Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).