Date de publication: 20 mai 2008
Promoteur – Intermédiaire Financier
Enerjisa Enerji Uretim A.S.
Lieu
Description
The construction and operation of several small and medium size Hydro Electric Power Plants with an expected installed capacity of more than 900 MW. The plants are either run of river or they have reservoir’s smaller than 15 square kilometres.
Objectifs
Support the development of renewable energy resources in Turkey and further develop the country’s hydro power potential.
Secteur(s)
Montant BEI envisagé (montant approximatif)
Up to EUR 135 million
Coût total (montant approximatif)
Estimated at EUR 700 million
Aspects environnementaux
If the project were located in the EU, it would fall under Annex II of the EIA Directive (85/337/EEC) as amended, requiring the competent national authority to determine the need for an EIA. In this case, as the installed capacity for each plant – except for two small run of river developments – is likely to exceed 50MW, they will require an EIA under national legislation.
Passation des marchés
Publication in the OJEU will be undertaken for items financed by the EIB, in line with the EIB Guide to Procurement.
Statut
Signé - 11/07/2008
Clause de non-responsabilité
Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).