    Référence: 20030169
    Date de publication: 16 avril 2003

    Promoteur – Intermédiaire Financier

    The City of Reykjavik

    Lieu

    Description

    Extension of the existing Nesjavellir geothermal cogeneration plant, located 25 km east of Reykjavik, by 30 MWe and 150 MWth, based on the results of a renewed assessment of the geothermal field.

    Objectifs

    The project concerns the further development of indigenous geothermal energy resources to generate electricity and heat, thereby minimising the use of fossil fuels and emissions of air pollutants. The capacity extension is aiming at the cost-effective supply of power and district heat to meet growing demand. It is also fully in line with the Bank’s policies on sustainable development (cogeneration of heat and power; renewable energy).

    Commentaires

    Environment.

    Secteur(s)

    Montant BEI envisagé (montant approximatif)

    Approximately EUR 23.5 million, equivalent to approximately ISK 2 billion.

    Coût total (montant approximatif)

    About EUR 47 million, equivalent to approximately ISK 4 billion.

    Aspects environnementaux

    The project, which would fall under Annex II of EU directive 97/11, is located in an isolated, unpopulated area on the slopes of the Hengill volcano. The competent government authority has ruled that a full environmental impact assessment (EIA) is not required in this case. The results of the EIA previously carried out for the existing plant and any environmental studies relating to the current extension will be reviewed during appraisal, including the potential impact on any nature conservation sites.

    Passation des marchés

    The promoter employs procurement procedures in line with the relevant EU Directive (93/38/EC), including the publication of tender announcements in the EC Official Journal. Given technical requirements to ensure standardisation of equipment design at the power plant, contracts for supply of the main equipment for the power plant extension have in this case been negotiated with the suppliers of the equipment originally installed, who were selected by open tendering procedures carried out in 1997.

    Statut

    Signé - 18/02/2004

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

    Mots-clés correspondants

    Islande Énergie