Référence: 20020458
Date de publication: 17 janvier 2003

Promoteur – Intermédiaire Financier

EniPower S.p.A.

Lieu

Description

The project concerns the design, construction and operation of the following combined cycle gas turbines (CCGT) in Italy:

  • Three 390 MWe units will be located inside the petrochemical site in Brindisi (Objective 1 area). Considering also the 3 existing units with a joint capacity of 81 MWe, the planned total installed capacity of this new plant will be 1,251 MWe. The project includes the construction of an 11.7-km 380-kV transmission line to connect the plant to the public grid (of which 1.1 km will be underground in order to minimise the environmental impact in the vicinity of urban areas).
  • Two 390 MWe units will be located inside the petrochemical site in Mantova. The planned total installed capacity of this new plant will thus be 780 MWe. The project includes the construction of an 8-km 380-kV transmission line to connect the plant to the public grid (of which 3 km will be underground to minimise the environmental impact in the vicinity of urban areas).

Objectifs

The project will improve the efficiency of electricity and heat production in Italy by the use of modern combined cycle technology (cogeneration). The addition of cost-effective generation capacity is particularly important in the context of market liberalisation, relatively high electricity tariffs and import requirements of 15% of domestic demand. The large majority of its electricity production of the two new plants will be delivered to the public grid, while steam will be supplied to the companies located in the same industrial site. The project will also reduce atmospheric emissions through the shutdown of conventional existing generation units.

Commentaires

Electricity generation

Secteur(s)

Montant BEI envisagé (montant approximatif)

Of the order of EUR 400 million

Coût total (montant approximatif)

Of the order of EUR 1000 million

Aspects environnementaux

Both power plants are undergoing a formal Environmental Impact Assessment process according to European legislation. The process is in the conclusive stage and available documents indicate significant emission reductions resulting from the shutdown of conventional existing generation units.

Passation des marchés

The promoter carries out formal international tendering for all works contracts and equipment following the relevant national legislation, including publication in the Official Journal of the European Communities when appropriate.

Statut

Signé - 16/05/2003

Clause de non-responsabilité

Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

Mots-clés correspondants

Italie Énergie