3 September 2010
Projektstatus
Referenz
Unterzeichnet | 21/12/2012
20090653
Projekttitel
Projektträger – Finanzintermediär
Gas Fired 400 MW Power Unit
Private company
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
Gesamtkosten (voraussichtlicher Betrag)
EUR 162 million.
EUR 400 million.
Beschreibung
Ziele
The project consists in a combined cycle gas turbine (CCGT) power station with an electric capacity of 400 MWe and heating capacity of 240 MWth.
The unit will provide electricity to the grid and heat to the neighbouring towns.
Umweltaspekte
Auftragsvergabe
Due to its capacity (plant over 300 MWth), the project is subject to the Annex I of the EIA Directive (85/337/EC and amendments) and was required to undergo a full Environmental Impact Assessment. The EIA is completed and the environmental permit was granted by the competent authorities.
The main project contractor will be chosen based on Public Procurement Law through negotiations with publication. The procedure will comply with the EU Directive 2004/17/EC.
Link zum projekt
Übersicht
Andere Links
Datenblätter
Weitere Veröffentlichungen
Weitere Veröffentlichungen
Zugehörige Pressemitteilungen
Aktuelles und Storys
Link zum projekt
Andere Links