Nom du projet
Promoteur – Intermédiaire financier
Giza North Power Plant
Egyptian Electricity Holding Company and subsidiaries.
Montant BEI envisagé (montant approximatif)
Coût total (montant approximatif)
EUR 300 million.
EUR 1 000 million.
Description
Objectifs
The project concerns the construction of a 1 500 MW gas-fired combined-cycle plant.
The project is expected to contribute to meeting growing electricity demand with a lower environmental impact than other fossil fuel based alternatives.
Aspects environnementaux
Passation des marchés
Due to its size and technical characteristics the project requires an Environmental Impact Assessment (EIA) under EIB Guidelines. The EIA process is ongoing and it is expected to be finalised in spring 2010.
The project is required to be procured in compliance with the Bank’s Guide to Procurement. The procurement process is commencing.