    The project consists of an electricity transmission line and a High Voltage Direct Current (HVDC) station that form an interconnection link between Armenia and Georgia. The link will allow continuous energy trade between the two countries, and in particular will allow Armenia to better access regional and European markets. The link will improve security of electricity supply in both participating countries.

    Ziele

    The project aims at providing a safe and economically efficient coverage of the growing electricity demand in both countries. Increasing energy security, in particular in Armenia, will contribute to economic development and provision of basic services to the population. By providing access to efficient electricity production and enabling the replacing of thermal power by hydropower (from Georgia), it also contributes to environmental and climate protection. One of its main objectives is to establish better energy interconnections by closing a missing link for a reliable, flexible and mutually beneficial cross-border energy exchange not only between Armenia and Georgia, but within the South Caucasus. The project will also introduce EU standards as it will allow the connection of Armenia (via Georgia) to the EU network (European Network of Transmission Systems Operators for Electricity - ENTSO-E). This project will foster regional integration, which is a strategic objective under the External Lending Mandate.

    Kommentar(e)

    This operation is covered by the EU Guarantee for EIB loans outside the EU.

    Sektor(en)

    Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

    EUR 10 million

    Gesamtkosten (voraussichtlicher Betrag)

    EUR 113 million

    Umweltaspekte

    An environmental and social impact assessment will be carried out fully in compliance with the Environmental Impact Assessment (EIA) Directive, including the identification and implementation of compensation and mitigation measures.

    Auftragsvergabe

    The contracts are expected to be procured by the promoter in accordance with KfW procurement rules and procedures, and in compliance with the requirements and standards agreed between EIB and KfW for projects under the Mutual Reliance Initiative for operations outside the EU, as foreseen in the Bank's Guide to Procurement. In particular, calls for international tenders will be published in the Official Journal of the EU in accordance with the Bank's Guide to Procurement.

    Projektstatus

    Unterzeichnet - 16/03/2015

    Haftungsausschluss

    Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
    Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

    Tags

    Armenien Energie