Projektträger – zwischengeschaltetes Finanzinstitut

Unión Fenosa SA

Ort

Beschreibung

The project comprises a large number of independent and geographically dispersed schemes for extending and modernising the promoter’s sub-transmission and distribution electricity networks. The project includes the implementation of 800 km of HV lines, 2700 km of MV lines, 3900 km of LV lines and 1800 MVA of MV/LV transformation capacity. The project capacity will be investigated in detail during appraisal. For the distribution network this will include the analysis of the overall capacities (km and MVA) of the different categories of network equipment (MV lines, LV lines and transformer stations). Description and capacity of the main sub-transmission project schemes (HV voltage lines and substations) will be analysed individually.

Ziele

The project will enable the promoter to cater for demand growth, to enable connection of new system users, and to improve the quality and the reliability of supply in a convergence area.

Sektor(en)

Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

Up to 50% of project cost.

Gesamtkosten (voraussichtlicher Betrag)

Approximately EUR 1 170 million.

Umweltaspekte

Some schemes of the project involving long 220 kV overhead lines will fall under Annex I of the EIA Directive while the remainder will fall under Annex II, leaving it to the national competent authority to decide whether an EIA would be required in line with the screening criteria specified in the directive. Many project schemes are expected to be distribution reinforcements that will not require EIAs and will have minimal or no environmental impact.

The impacts that can be typically expected for the project schemes relate to visual impact, vegetation clearance, impact on flying vertebrates, electromagnetic fields, noise nuisance, and disturbance during construction. The EIA screening criteria applied by the national competent authority in Spain and the provisions for biodiversity assessment of projects will be investigated during appraisal.

Auftragsvergabe

The promoter is subject to the Public Procurement Act of Spain (Ley 31/2007) that came into force in October 2007 transposing the EU Directives on public procurement. The promoter’s approach for procurement of goods and services in the distribution sectors will be evaluated during appraisal.

Projektstatus

Unterzeichnet - 11/06/2010

Haftungsausschluss

Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

Tags

Spanien Energie