    Référence: 20120214
    Date de publication: 20 septembre 2013

    Promoteur – Intermédiaire Financier

    The Slovak Republic through the Ministry of Transport. ŽSR (Železnice Slovenskej Republiky), the Slovak Railway company, is the implementing body for the project.

    Lieu

    Description

    This major project aims at modernising a 17.5 km railway section between Nové Mesto nad Váhom and Zlatovce.

    Objectifs

    The project will contribute towards an overall improvement of the urban environment by encouraging the use of rail transport for both passengers and freight, thus reducing private car usage and road freight.

    Commentaires

    Secteur(s)

    Montant BEI envisagé (montant approximatif)

    EUR 34 million

    Coût total (montant approximatif)

    EUR 340 million

    Aspects environnementaux

    The project, modernisation of an existing railway, falls under Annex II of the EIA Directive Directive 2011/92/EU, is subject to an EIA depending on the decision of a screening procedure, determined by the competent authorities. The Ministry of Environment of the Slovak Republic, as the Competent Authority (CA) determined that the project would be subject to EIA under national regulations prevailing in 2002 (the national EIA Act 127/1994 further amended and completed by Act 391/2000) and an EIA was carried out and approved in 2003 for the complete Nové Mesto nad Váhom – Púchov section. The project is not expected to have an impact on Natura 2000 areas, as has been confirmed by the Competent Authority.

    Passation des marchés

    EU procurement directives have been transposed into Slovak legislation. The contract notices for the international open tender were published in the Official Journal of the European Union (OJEU). The procurement process is accountable under the Cohesion Funds regulations and is acceptable to the Bank.

    Statut

    Approuvé - 25/10/2013

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).