Suche starten De menü de ClientConnect
Suche starten
Ergebnisse
Top-5-Suchergebnisse Alle Ergebnisse anzeigen Erweiterte Suche
Häufigste Suchbegriffe
Meistbesuchte Seiten
Referenz: 20170145
Veröffentlichungsdatum: 22 März 2018

Projektträger – zwischengeschaltetes Finanzinstitut

MINISTERE DE L'EQUIPEMENT,DE L'AMENAGEMENT DU TERRITOIRE

Ort

Beschreibung

The project concerns the widening of an 8.2-km long section of the main southern road access to the city of Tunis as well as the construction of three new interchanges in the feeder roads RN3, RN3E1 and Route X. The project is a major allocation under the framework loan 20150308 Modernisation Routière II.

Ziele

The project will contribute to the upgrading and expansion of key urban road sections in the city of Tunis, increasing competitiveness through the provision of essential infrastructure. The project meets the Bank's priority objectives for transport lending and is in line with the Bank's objectives.

Sektor(en)

Garantie im Rahmen des Außenmandats

This operation is covered by the ELM Guarantee.

Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

EUR 30 million

Gesamtkosten (voraussichtlicher Betrag)

EUR 65 million

Umweltaspekte

If located within the EU, the project would fall under Annex I of the Environmental Impact Assessment (EIA) Directive 2011/92/EC, thus requiring a full EIA. One main EIA procedure including a public consultation was carried out. The environmental permit was granted by the competent authority in July 2017. The Bank shall investigate environmental and social aspects during the appraisal and verify that the promoter has followed the relevant EU environmental and social principles, standards and practices. The Bank shall also verify the acceptability of the project in terms of likely environmental impacts and proposed mitigation and compensation measures.

Auftragsvergabe

The Bank will require the promoter to ensure that implementation of the project will be done in accordance with the Bank's Guide to Procurement.

Projektstatus

Genehmigt - 15/05/2018

Haftungsausschluss

Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

Tags

Tunesien Verkehr