Veröffentlichungsdatum: 14 März 2016
Projektträger – zwischengeschaltetes Finanzinstitut
FINA ENERJI HOLDING ASOrt
Beschreibung
Construction of three wind-power plants in Turkey (Uluborlu, Kizilcaterzi and Karova) for a total capacity of 106MW, together with associated facilities, power substations and interconnection lines
Ziele
Generation of electricity from onshore wind farms
Sektor(en)
- Energie - Energieversorgung
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
EUR 50 million
Gesamtkosten (voraussichtlicher Betrag)
EUR 131 million
Umweltaspekte
The Bank will review the environmental and social assessments and corresponding authorisation processes during appraisal, including a verification of compliance with its environmental and social standards.
Auftragsvergabe
The Bank will require the promoter to ensure that any procurement procedures are done in accordance with the Bank's Guide to Procurement.
Projektstatus
Unterzeichnet - 28/10/2016
Haftungsausschluss
Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).