Veröffentlichungsdatum: 13 Dezember 2013
Projektträger – zwischengeschaltetes Finanzinstitut
MAVIR MAGYAR VILLAMOSENERGIA-IPARI ATVITELI RENDSZERIRANYITO ZRTMAGYAR FOLDGAZTAROLO ZRT
Ort
Beschreibung
Reinforcement and extension of Hungary's electricity transmission network during 2013-2018 and reconstructure works on the underground gas storages.
Ziele
Economic and Social Cohesion (transversal)
Competitive and Secure Energy (incl. TEN-E)
Sektor(en)
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
EUR 100 million
Gesamtkosten (voraussichtlicher Betrag)
EUR 203 million
Umweltaspekte
Some of the project schemes fall under Annex I of the EIA Directive 2011/92/EU, requiring an EIA. Other project schemes fall under Annex II; therefore the Competent Authority has to decide whether an EIA is required. The status and available results of the environmental impact studies and the authorisation processes as well as the actual impacts, including potential negative impacts on sites of importance of nature or cultural heritage conservation, and the planned mitigating and/or compensating measures will be reviewed during appraisal.
Auftragsvergabe
The Bank will require the Promoter to ensure that contracts for the implementation of the project have been/shall be tendered in accordance with the relevant applicable EU procurement legislation 2004/17/EC and Dir. 2007/66/EC (amending Directives 1989/665/EEC and 1992/13/EEC), with publication of tender notices in the EU Official Journal, as and where required.
Projektstatus
Unterzeichnet - 12/12/2014
Haftungsausschluss
Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).