    Investments under the promoter's 2014-2018 investment plan, aiming at the extension and reinforcement of the electricity transmission network throughout Portugal.

    Ziele

    The programme is expected to enable the integration into the grid of new renewable generation resources, support the efficient operation of the electricity market in the Iberian Peninsula and contribute to improving the reliability of supply.

    Kommentar(e)

    Sektor(en)

    Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

    EUR 170 million

    Gesamtkosten (voraussichtlicher Betrag)

    EUR 350 million

    Umweltaspekte

    By their technical characteristics, some programme schemes fall under Annex I or Annex II of the Environmental Impact Assessment Directive. The impacts that can be typically expected for these sub-projects relate to visual impact, vegetation clearance, electromagnetic fields, noise nuisance, impact on flying vertebrates and disturbance during construction. Environmental impact studies will be carried out as applicable and mitigating and/or compensation measures will be applied as necessary.

    Auftragsvergabe

    The Bank will require the promoter to ensure that contracts for the implementation of the project have been/shall be tendered in accordance with the relevant applicable EU procurement legislation (Dir. 2004/17/EC and Dir. 2007/66/EC [amending Directives 1989/665/EEC and 1992/13/EEC]), with publication of tender notices in the EU Official Journal, as and where appropriate.

    Projektstatus

    Unterzeichnet - 25/11/2015

    Haftungsausschluss

    Before financing approval by the Board of Directors, and before loan signature, projects are under appraisal and negotiation. The data provided on this page is therefore indicative and cannot be considered to represent official EIB policy (see also the Explanatory notes).