Veröffentlichungsdatum: 10 Dezember 2012
Projektträger – zwischengeschaltetes Finanzinstitut
GAS NATURAL SDG SAOrt
Beschreibung
Reinforcement and extension of the electricity distribution network in four Spanish regions (Castilla La mancha, Castilla y León, Galicia - all three convergence regions - and Madrid) during the period 2012-2015.
Ziele
Reinforcement and extension of the electricity distribution network in four Spanish regions.
Sektor(en)
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
EUR 475 million
Gesamtkosten (voraussichtlicher Betrag)
EUR 977 million
Umweltaspekte
Most of the project schemes relate to Medium Voltage (MV) and Low Voltage (LV) and therefore fall under Annex 2 of the EIA Directive 92/2011/EU. Such schemes are expected to have minimal or null environmental impacts.
The project includes also high voltage schemes - lines and substations - that requires an Environmental Impact Assessment following Annex 1 of the EU EIA Directive 92/2011/EU.
Auftragsvergabe
The Bank will require the Promoter to ensure that contracts for the implementation of the project have been/shall be tendered in accordance with the relevant applicable EU procurement legislation (Dir 2004/18/EC/ or 2004/17/EC and Dir. 2007/66/EC), with publication of tender notices in the EU Official Journal, as and where appropriate.
Projektstatus
Unterzeichnet - 9/07/2013
Haftungsausschluss
Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).