    Référence: 20240325
    Date de publication: 1 juillet 2024

    Promoteur – Intermédiaire Financier

    MFW BALTYK II SP ZOO,MFW BALTYK III SP ZOO

    Lieu

    Description

    The project concerns the design, implementation and operation of two very large-scale, fixed-bottom offshore windfarms (Baltyk II and Baltyk III) with a capacity of up to 720 MW each, located off the Ustka-Leba coast of Northern Poland.

    Objectifs

    The offshore wind farms will primarily reduce carbon and air pollution emissions, which are externalities the market fails to address. By supporting the introduction in the market of new variable renewable generation technologies, the project will fill a market gap in the development of new renewable capacity.

    Secteur(s)

    • Énergie - Production et distribution d'électricité, de gaz, de vapeur et d'air conditionné

    Montant BEI envisagé (montant approximatif)

    not disclosed

    Coût total (montant approximatif)

    not disclosed

    Aspects environnementaux

    Wind farms adhere to the national legislation having transposed Annex II of Environmental Impact Assessment (EIA) Directive 2014/52/EU (amending EU Directive 2011/92/EU), thereby leaving it to the competent authority to determine if an EIA is mandatory. Given the projects size, the competent authority required an EIA to be conducted. Compliance of the authorisation process with relevant EU Directives will be verified during appraisal.

    Passation des marchés

    It is provisionally understood that the promoters, which are two Special Purpose Vehicles (SPV), are neither a contracting authority nor a public undertaking (in the sense of the EU procurement policies). The promoters do not seek to operate on the basis of special or exclusive rights granted by a competent authority in relation to this project. This will be confirmed during appraisal.

    Statut

    À l'examen - 31/05/2024

    Milestone
    À l'examen

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

    Mots-clés correspondants

    Pologne Énergie