Veröffentlichungsdatum: 21 Mai 2024
Projektträger – zwischengeschaltetes Finanzinstitut
OFFICE NATIONAL DE L'ELECTRICITE ETOrt
Beschreibung
The project consists of a multi component investment programme covering the period 2024-2029, that includes several electricity transmission schemes, from 60 kV to 400 kV, geographically dispersed throughout the country.
Ziele
The aim is to reinforce and extend the country's electricity infrastructure (transmission lines and substations) by reducing losses, enhancing reliability and meeting new electricity demand. Additionally, the programme includes the integration of new renewable electricity generation capacity that will ensure a more sustainable and efficient power system.
Sektor(en)
- Energie - Energieversorgung
Under Global Europe NDICI guarantee
Under EFSD+ Guarantee
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
EUR 170 million
Gesamtkosten (voraussichtlicher Betrag)
EUR 355 million
Umweltaspekte
The envisaged sub-projects (new transmission lines and substations from 60 kV to 400 kV) are expected to require a full Environmental and Social Impact Assessment (ESIA) study in accordance with national law. The exact requirements and status of the permitting procedures will also be further assessed during the appraisal. The promoter shall comply with EIB's Environmental and Social standards.
Auftragsvergabe
The promoter has to ensure that the project implementation will be done in accordance with the EIB's Guide to Procurement.
Projektstatus
Unterzeichnet - 22/05/2025