    Référence: 20180392
    Date de publication: 14 août 2018

    Promoteur – Intermédiaire Financier

    BANDWIDTH AND CLOUD SERVICES GROUP HOLDINGS

    Lieu

    Description

    The project concerns the deployment of fibre optics networks in regions of Eastern Africa where, either these kinds of networks are not available, or they are expensive and unreliable. In both cases, the development of digital services enabled by broadband access is limited. In total, the networks deployed will have a total length of more than 4 850 km, including more than 3 850 km of terrestrial fibre cable and around 1 000 km of submarine cable in Lake Tanganyika and Lake Albert.

    Objectifs

    The project will lead to the deployment of five different fibre optics networks in Kenya, Rwanda Uganda, Zambia and the Democratic Republic of the Congo (DRC). In total, the networks deployed will have a total length of around 4,850 km, including 3,850 km of terrestrial fibre cable and around 1,000 km of submarine cable in Lake Tanganyika and Lake Albert.

    Secteur(s)

    Montant BEI envisagé (montant approximatif)

    USD 18 million (EUR 16 million)

    Coût total (montant approximatif)

    USD 46 million (EUR 41 million)

    Aspects environnementaux

    If located in the EU, the project would not require an Environmental Impact Assessment as per Directive 2014/52/EU amending the EIA Directive 2011/92/EU, however environmental assessments might be required according to national law, in particular for the submarine cable segment in Lake Tanganyika. In any case, there is no relevant negative residual environmental impact expected. Nevertheless, the environmental details including the CO2 footprint (if needed) and other possible impacts will be assessed during the appraisal.

    Passation des marchés

    The Bank will require the promoter to ensure that implementation of the project will be done in accordance with the Bank's Guide to Procurement.

    Statut

    Signé - 22/11/2018

    Clause de non-responsabilité

    Avant d’être approuvés par le Conseil d’administration et avant la signature des prêts correspondants, les projets font l’objet d’une instruction et de négociations. Par conséquent, les informations et données fournies sur cette page sont indicatives.
    Elles sont fournies à des fins de transparence uniquement et ne peuvent être considérées comme représentant la politique officielle de la BEI (voir également les notes explicatives).

    Mots-clés correspondants

    Régional - Afrique Télécom