Referenz: 20140100
Veröffentlichungsdatum: 13 Oktober 2014

Projektträger – zwischengeschaltetes Finanzinstitut

LITGRID AB

Ort

Beschreibung

The project consists of the Lithuanian part of the Lithuania-Poland asynchronous interconnector, known as LitPol Link, and the associated reinforcement of the Lithuanian electricity network. LitPol Link comprises the construction of a 500 MW back-to-back station at Alytus in south-western Lithuania and the erection of a double-circuit 400 kV overhead line (OHL) from Alytus to Elk in north-eastern Poland. The route length of the OHL is 163 km, of which 51 km will be erected in Lithuania from Alytus to the Polish border. The associated network reinforcement encompasses the construction of a 53 km-long, double-circuit 330 kV OHL connecting Alytus to Kruonis.

Ziele

This is a key operation to support Lithuania’s energy strategy and to implement the Baltic Energy Market Interconnection Plan.

Sektor(en)

Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

EUR 65 million

Gesamtkosten (voraussichtlicher Betrag)

EUR 132 million

Umweltaspekte

The project falls under Annex I of the Environmental Impact Assessment (EIA) Directive. The impacts that can be typically expected for the project relate to visual impact, vegetation clearance, electromagnetic fields, noise nuisance, bird collision and mortality and disturbance during construction. Environmental impact studies have been carried out and mitigating and/or compensation measures will be applied as necessary.

Auftragsvergabe

The Bank will require the promoter to ensure that contracts for the implementation of the project have been/shall be tendered in accordance with the relevant applicable EU procurement legislation (Dir. 2004/17/EC and Dir. 2007/66/EC (amending Directives 1989/665/EEC and 1992/13/EEC)), with publication of tender notices in the EU Official Journal, as and where required.

Projektstatus

Unterzeichnet - 18/12/2014

Haftungsausschluss

Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.