    Referenz: 20230790
    Veröffentlichungsdatum: 23 Mai 2024

    Projektträger – zwischengeschaltetes Finanzinstitut

    TERNA - RETE ELETTRICA NAZIONALE SPA

    Ort

    Beschreibung

    The project will support the renewal of the Italian electricity transmission network. The investment programme, to be implemented by 2026, mainly concerns assets reaching the end of their technical life and therefore being at a great risk of failure.

    Additionality and Impact

    The Project comprises investments in the electricity transmission network in Italy over the period 2023-2026. The Project addresses the needs for the renewal of existing assets and planned development, including reinforcement of overhead lines, replacement of asset components and undergrounding. The Project contributes to maintaining or increasing security of supply by reducing the risk of supply interruptions, and it contributes to climate adaptation. Part of the investment will benefit transition and less developed "Cohesion" regions in Italy.

    The support of the Bank brings a substantial financial benefit to the Project by lowering the associated cost of funding and offering a tenor longer than the one usually available in the market. The EIB financial value added is even more tangible under the ongoing market instability and turmoil generated by current geopolitical situation.

    Ziele

    The aim is to replace obsolete components (e.g. conductors, transformers, supports, among others) with more modern and efficient ones, to improve the network resilience to adverse climate events and the overall stability and reliability of the national transmission system.

    Sektor(en)

    Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

    EUR 400 million

    Gesamtkosten (voraussichtlicher Betrag)

    EUR 812 million

    Umweltaspekte

    Some of the schemes of the programme may fall under Annex II of the Environmental Impact Assessment (EIA) directive. No EIA is expected according the national legislation as the promoter indicated that no scheme will be above 100 kV with a length of more than 3 Km and renewal of underground cables with a length above 40 km. The environmental and social due diligence will focus on the promoters' capacity to implement the programme in line with EIB's environmental and social standards and requirements.

    Auftragsvergabe

    The Bank will require the Promoter to ensure that contracts for the implementation of the Project are tendered in accordance with the applicable EU procurement legislation, Directive 2014/25/EU as well as Directive 92/13/EEC as interpreted by the Court of Justice of the EU, with publication of tender notices in the EU Official Journal, as and where required.

    Projektstatus

    Unterzeichnet - 24/10/2024

    Milestone
    In Prüfung
    Genehmigt
    Unterzeichnet
    16 Oktober 2024
    24 Oktober 2024

    Haftungsausschluss

    Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
    Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

    Tags

    Italien Energie