Veröffentlichungsdatum: 7 November 2017
Projektträger – zwischengeschaltetes Finanzinstitut
EUSTREAM ASOrt
Beschreibung
The project consists of the construction and operation of the Slovak section of the Poland-Slovakia bi-directional gas interconnector and modification of the existing compressor station Velke Kapusany.
Ziele
The project will improve the security of supply, flexibility and interoperability of the interconnected gas networks in the region.
Sektor(en)
- Energie - Energieversorgung
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
EUR 70 million
Gesamtkosten (voraussichtlicher Betrag)
EUR 144 million
Umweltaspekte
The promoter has carried out an Environmental Impact Assessment (EIA) for the Slovak section of the Poland-Slovakia gas interconnector and the environmental permit has been issued by the competent authority. The permitting will be further investigated during appraisal to ensure compliance with the Bank's Environmental and Social Standards.
Auftragsvergabe
The investments under the project are subject to the national and EU procurement provisions defined for entities operating in the water, energy, transport and postal services sectors.
Projektstatus
Unterzeichnet - 27/12/2017