    SOCIETÉ NATIONALE D'EXPLOITATION ET DE DISTRIBUTION DES EAUX SA

    Ort

    Beschreibung

    The project aims to secure drinking water supply in Greater Tunis through the construction of a water treatment plant in Béjaoua and related infrastructure, including water pipes for the financial port of Tunis.

    Ziele

    In order to meet the drinking water needs of the Greater Tunis area during peak periods until 2030, EIB and Agence française de développement (AFD) will support SONEDE, Tunisia's national water utility company, to implement a program aiming to strengthen and secure the water supply of the Greater Tunis that includes the following elements: - Construction of a water pumping station and a drinking water treatment plant in Béjaoua with a capacity of 4 m3/s; - Supply of 52.2km of pipes for the transfer of treated water; and - Construction of six reservoirs with a capacity of 10,000 m3 each.

    Kommentar(e)

    Each of EIB and AFD will provide two distinct loans to the Republic of Tunisia and to SONEDE to finance the project. The project will be covered by a first demand guarantee issued by the Republic of Tunisia, for the EIB loan granted to SONEDE to finance the Béjaoua Station. SONEDE is expected to finance the construction of the Bejaoua Station (est. project costs of EUR 50m, taxes excluded). The Republic of Tunisia is expected to finance the Tunis Financial Harbour components (est. project costs of EUR 29m, taxes excluded).

    Sektor(en)

    • Wasser, Abwasser - Wasserversorgung; Abwasser- und Abfallentsorgung und Beseitigung von Umweltverschmutzungen

    Garantie im Rahmen des Außenmandats

    This operation is covered by the ELM Guarantee.

    Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

    EUR 38 million

    Gesamtkosten (voraussichtlicher Betrag)

    EUR 79 million

    Umweltaspekte

    The proposed investment will focus on increasing the capacity of the water supply facility for the Grand Tunis area (production, transport and storage). Where required, full Environmental and Social Impact and Assessments (ESIAs) will be carried out as well as any required environmental and social management plans (ESMPs). Details will be assessed during appraisal.

    Auftragsvergabe

    EIB will require the promoter to ensure that implementation of the project will be done in accordance with the EIB Guide to Procurement.

    Projektstatus

    Unterzeichnet - 21/10/2020

    Haftungsausschluss

    Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
    Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

    Tags

    Tunesien Wasser, Abwasser