Referenz: 20160146
Veröffentlichungsdatum: 25 April 2017

Projektträger – zwischengeschaltetes Finanzinstitut

SVENSKA CELLULOSA AB SCA (PUBL)

Ort

Beschreibung

The operation consists (i) in the finance of selected renewable energy, energy efficiency and environmental protection measures within an investment programme in Sweden consisting of the upgrade of a pulp mill in Timrå and (ii) the replanting and regeneration of about 68,000 ha of forest, the construction of 4,250 km of forest roads and an upgrade of five forest terminals.

Ziele

The project will contribute to higher energy efficiency and innovative process optimisation. The operation also aims to upgrade and renew regional forest resources and will enhance and create employment and have significant multiplier effects on the regional rural economies.

Sektor(en)

Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

EUR 150 million

Gesamtkosten (voraussichtlicher Betrag)

EUR 684 million

Umweltaspekte

The mill modernisation project falls under Annex I of Environmental Impact Assessment (EIA) Directive 2011/92/EU. A full EIA as well as a permit under the Industrial Emission Directive 2010/75/EU is required. Some of the investments planned within the project programme for modernisation and renewal of forest assets may fall under Annex II of the EIA Directive and would require a screening decision by the competent authority. Details of the permitting procedures, potential impact on nature conservation sites close by and sustainability and origin of the biomass will be further assessed at appraisal.

Auftragsvergabe

The Bank will require the promoter to ensure that contracts for the implementation of the project have been/will be tendered in accordance with the relevant applicable EU procurement legislation.

Projektstatus

Unterzeichnet - 17/11/2017

Haftungsausschluss

Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

Tags

Schweden Industrie Landwirtschaft, Fischerei, Forstwirtschaft