Veröffentlichungsdatum: 5 April 2016
Projektträger – zwischengeschaltetes Finanzinstitut
AUTORITA PORTUALE DELLA SPEZIAOrt
Beschreibung
The project is a sub-operation of the TEN-T medium-sized Italian ports programme loan. The works consist of the rail development within the port as detailed in the port's current master plan.
Ziele
The project will contribute to the development of a core TEN-T port, promotion of sustainable transport and climate action: improving supply chain efficiency and encouraging transfer of freight from road to railway.
Sektor(en)
- Verkehr - Verkehr und Lagerei
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
EUR 30 million
Gesamtkosten (voraussichtlicher Betrag)
EUR 43 million
Umweltaspekte
An environmental impact assessment (EIA) for the project was undertaken and approved as part of the 2006 port master plan. The approval required a number of issues to be investigated further. This work was completed and final approval was granted in April 2015 for the project railway works.
Auftragsvergabe
The promoter is a contracting authority, as referred to in Article 8 of Directive 2004/17/EC governing the procurement and procedures for entities operating in the public sector. Therefore, all contracts financed by means of this project are to be tendered in accordance with this directive, with publication of tender notices in the Official Journal of the EU, as and where appropriate.
Projektstatus
Unterzeichnet - 20/09/2016
Haftungsausschluss
Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).