    Referenz: 20140463
    Veröffentlichungsdatum: 21 April 2015

    Projektträger – zwischengeschaltetes Finanzinstitut

    DUBLIN PORT CO

    Ort

    Beschreibung

    Infrastructure works in the port of Dublin to accommodate traffic growth and prepare for increases in ship size, including construction of new quays and jetties, reclamation works and deepening of the access channel.

    Ziele

    The main objective of the project is to improve operations and increase capacity for roll-on-roll-off freight traffic in the port of Dublin in response to market demand. The project will adapt existing port infrastructure approaching the end of its useful life.

    Sektor(en)

    Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

    EUR 100 million

    Gesamtkosten (voraussichtlicher Betrag)

    EUR 200 million

    Umweltaspekte

    An environmental impact statement has been prepared for the project.

    A Natura impact statement (NIS) has also been prepared for the project. It considered the potential for significant impact arising from the proposed Alexandra Basin Redevelopment and associated capital dredging scheme that would have the potential to adversely affect any Natura 2000 site. The proposed project works do not lie within any Natura 2000 designation; however, they are in close proximity to four sites. The potential for direct, indirect and cumulative impact affecting the Natura 2000 sites was assessed and where necessary mitigation measures were considered.

    The NIS concluded that the proposed project with the implementation of the prescribed mitigation measures would not give rise to significant impact, either individually or in combination with other plans and projects, in a manner which would adversely affect the integrity of any designated site within the Natura 2000 network.

    These findings will be verified during the appraisal.

    The project’s compliance with the Strategic Environmental Assessment (SEA) Directive 2001/42/EC, Environmental Impact Assessment (EIA) Directive 2011/92/EC, the Habitats Directive 92/43/EEC and the Birds Directive 79/409/EEC, including the status of any environmental studies and public consultation, mitigation/compensation measures, environmental monitoring plans and biodiversity assessment requirements will be verified during appraisal.

    Auftragsvergabe

    The Bank will require the promoter to ensure that any procurement procedures are undertaken in accordance with the Bank’s Guide to Procurement.

    Projektstatus

    Unterzeichnet - 21/12/2015

    Haftungsausschluss

    Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
    Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

    Tags

    Irland Verkehr