    Projektträger – zwischengeschaltetes Finanzinstitut

    AB FORTUM VAERME HOLDING SAMAEGT MED STOCKHOLMS STAD

    Ort

    Beschreibung

    Construction of a new biofuel-fired CHP plant in Stockholm.

    Ziele

    The project comprises the design, construction, operation and maintenance of a new biomass combined heat and power (CHP) plant including the necessary upgrading of harbour infrastructure. It will be located in the city of Stockholm and delivering heat to the existing district heating system in Stockholm and electricity to the public grid. The power plant allows for the use of a full range of solid biomass but production is expected to be based on mainly wood chips. The new CHP plant will have a production capacity of 280 MWth heat and 130 MWe electricity.

    Sektor(en)

    Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

    EUR 260 million

    Gesamtkosten (voraussichtlicher Betrag)

    EUR 543 million

    Umweltaspekte

    The power plant and its biomass reception and processing infrastructures will be erected inside an existing industrial facility. By virtue of its technical characteristics, the project falls under Annex II of the Directive 2011/92/EU. Here, the Competent Authority requested an EIA for the power plant. Based upon the outcomes of the EIA, the project’s environmental consent was granted in November 2007.

    Auftragsvergabe

    The promoter falls under the Utilities Directive 2004/17/EC and is obliged to apply public procurement procedures. Compliance with the Utilities Directive has been stated by the promoter and will be verified during appraisal.

    Projektstatus

    Unterzeichnet - 17/06/2014

    Haftungsausschluss

    Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
    Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

    Tags

    Schweden Energie