Veröffentlichungsdatum: 8 September 2011
Projektträger – zwischengeschaltetes Finanzinstitut
AS Eesti Energia
Ort
Beschreibung
The project consists of a 220 kt/yr one line waste incineration plant with net energy recovery capacities of 17MW electrical and 50 MW thermal (for district heating).
Ziele
This will be the first waste incineration plant in Estonia. It will reduce the amount of waste that is currently landfilled. Electricity generated at the facility will be delivered to the grid, and heat to the district heating system.
Sektor(en)
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
EUR 50 million
Gesamtkosten (voraussichtlicher Betrag)
Approximately EUR 110 million
Umweltaspekte
The project falls under Annex 1 of the EIA directive, and accordingly an EIA is required. The EIA process (including public participation) has been completed, and the EIA was approved in October 2007 by the Environmental Board, which is the competent authority.
Auftragsvergabe
The promoter is a public sector controlled entity and thereby required to follow Utilities Directive 2004/17/EC in the procurement.
Projektstatus
Unterzeichnet - 8/12/2011
Haftungsausschluss
Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).