Veröffentlichungsdatum: 3 Oktober 2011
Projektträger – zwischengeschaltetes Finanzinstitut
ASFINAG
Ort
Beschreibung
Construction of a 22 km section of the S10 Mühlenviertler Schnellstraße between Unterweitersdorf and Freistadt.
Ziele
The S10 Mühlviertler Schnellstrasse will link the Upper Austrian central area around the city of Linz and the Czech capital-region of Prague. It aims at:
- a better integration of the region through efficient road-connections,
- generating new economic inputs
- improving current traffic situation from a congestion, safety and environmental point of view.
Sektor(en)
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
EUR 400 million
Gesamtkosten (voraussichtlicher Betrag)
EUR 808 million
Umweltaspekte
The applicability of the SEA Directive is to be assessed during appraisal. The project is subject to Annex I of the EIA Directive 85/337/EEC as amended. An EIA has been carried out and public consultations have been extensively organised. Environmental approval has been granted by the competent authority in July 2007. A Natura 2000 site lies in the vicinity of the project (Tal der Kleinen Gusen). The EIA procedure, including issues related to the Habitats and Birds Directives, will be assessed during appraisal.
Auftragsvergabe
The Promoter is a public entity and is therefore subject to EU Procurement Directives. In this context, the Bank will require the promoter to ensure that the contracts related to the project have been or shall be tendered in accordance with EU public procurement procedures. To be reviewed at appraisal.
Projektstatus
Unterzeichnet - 12/12/2011
Haftungsausschluss
Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).