Suche starten De menü de ClientConnect
Suche starten
Ergebnisse
Top-5-Suchergebnisse Alle Ergebnisse anzeigen Erweiterte Suche
Häufigste Suchbegriffe
Meistbesuchte Seiten
    Referenz: 20090232
    Veröffentlichungsdatum: 14 Februar 2011

    Projektträger – zwischengeschaltetes Finanzinstitut

    Metropolitan Community of Montpellier (Communauté d'A gglomération de Montpellier)

    Ort

    Beschreibung

    The project consists of the construction of a third 22 km tramway line with 31 stops and the 0.5 km westward extension of Line 1. Line III will cross four municipalities in succession: Montpellier, Lattes, Pérols and Juvignac. The project also includes the acquisition of 23 40m-long tram-sets, each with a capacity of 300 passengers. Urban development and landscaping measures form an integral part of the project.

    Ziele

    The project consists of the construction of a third 22 km tramway line with 31 stops and the 0.5 km westward extension of Line 1. Line III will cross four municipalities in succession: Montpellier, Lattes, Pérols and Juvignac. The project also includes the acquisition of 23 40m-long tram-sets, each with a capacity of 300 passengers. Urban development and landscaping measures form an integral part of the project.

    Sektor(en)

    Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

    EUR 250 million.

    Gesamtkosten (voraussichtlicher Betrag)

    EUR 530 million.

    Umweltaspekte

    The project comes under Annex II to Directive 85/337/EEC amended, which stipulates that the competent national authorities must decide whether an environmental impact assessment (EIA) is to be conducted. Under French law, the project is subject to an impact assessment as part of the Declaration of Public Interest (DUP) procedure. This procedure was completed in June 2007 and the project obtained a favourable opinion from the various government departments, including the environmental authority.

    Auftragsvergabe

    Procurement procedures will be in accordance with national legislation and EU directives.

    Projektstatus

    Unterzeichnet - 4/07/2011

    Haftungsausschluss

    Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
    Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

    Tags

    Frankreich Verkehr