Veröffentlichungsdatum: 8 Juni 2007
Projektträger – zwischengeschaltetes Finanzinstitut
PLINACRO d.o.o., ZagrebOrt
Beschreibung
The second phase (2007 – 2011) of investment programme for the modernisation and expansion of the natural gas transmission system. It includes approximately 930 km of new high pressure gas pipelines.
Ziele
The project forms part of the Croatian national energy plan for the expansion of the national gas transmission system in order to meet the expected growth in gas demand and reinforce the security of gas supply.
Kommentar(e)
Transport via pipelines (gaslines).
Sektor(en)
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
EUR 190 million.
Gesamtkosten (voraussichtlicher Betrag)
EUR 450 million.
Umweltaspekte
A number of Environmental impact studies are being carried out for the various sections of the new gas pipelines. It will be verified during appraisal that the overall EIA process is in line with the EU acquis on Environmental Impact and in particular with regard to public consultation.
Auftragsvergabe
All main contracts will be procured through international competitive bidding, in line with the EIB requirements.
Projektstatus
Unterzeichnet - 31/07/2007
Haftungsausschluss
Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).