Veröffentlichungsdatum: 27 November 2006
Projektträger – zwischengeschaltetes Finanzinstitut
Centrica plcOrt
Beschreibung
Construction of a 840MW gas-fired combined cycle power station as well as associated gas pipeline and electricity transmission infrastructure.
Ziele
Installation of a modern power generation unit with high energy efficiency and low environmental impact to improve the energy demand/supply balance.
Kommentar(e)
Electricity, Gas and Water Supply
Sektor(en)
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
Up to GBP 150 million.
Gesamtkosten (voraussichtlicher Betrag)
Around GBP 400 million.
Umweltaspekte
The project falls under Annex 1 of Directive 97/11/EC and has undergone a full EIA procedure, including public consultation. This procedure has been completed and the competent authority issued the development consent with a number of conditions, which will be implemented by the promoter.
Auftragsvergabe
The turn-key contract for design and execution of the power plant was published in the OJEU for tendering under a negotiated procedure.
Projektstatus
Unterzeichnet - 1/06/2007
Haftungsausschluss
Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).