    Referenz: 20060152
    Veröffentlichungsdatum: 21 März 2007

    Projektträger – zwischengeschaltetes Finanzinstitut

    Société Nationale des Eaux du Bénin. (SONEB)

    Ort

    Beschreibung

    The project involves the development of infrastructure to improve the drinking water supply system of Cotonou and the suburban municipalities of Abomey Calavi and Seme Kpodji in southern Benin. It will also assist the construction of 3 500 standalone sanitation facilities in the most deprived areas of greater Cotonou.

    Ziele

    The project aims to increase the rate of access to drinking water in greater Cotonou from 56% in 2006 to 66% in 2011, thereby enabling over 220 000 people to benefit directly from the project. The standalone sanitation facilities will concern 30 000 inhabitants.

    Sektor(en)

    Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

    EUR 13 million.

    Gesamtkosten (voraussichtlicher Betrag)

    EUR 26 million.

    Umweltaspekte

    In connection with the application to the Water Facility for a subsidy for this project, a preparatory study was carried out to evaluate the environmental impact of the planned works and proposed mitigants. Nonetheless, the project will also be subject to an EIA under Benin law, which makes such an assessment compulsory for major projects, including those with an impact on natural water resources. This EIA must be approved by the Benin Environment Agency before the work begins.

    Auftragsvergabe

    The tendering procedures applied for this project will be those of the EIB, the lead lender, in accordance with the provisions of the ACP-EU Water Facility. The major works will be put out to international tender with publication in the OJEU. The other works will be put out to tender nationally, in accordance with the size of the contract.

    Projektstatus

    Unterzeichnet - 13/12/2007

    Haftungsausschluss

    Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
    Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

    Tags

    Benin Wasser, Abwasser