Veröffentlichungsdatum: 22 Oktober 2009
Projektträger – zwischengeschaltetes Finanzinstitut
Communauté Electrique du BéninOrt
Beschreibung
Construction of 308 km of 161 kV lines, 5 km of 63 kV underground cables and 1 substation, the refurbishment of 289 km of 161 kV lines, and the refurbishment/enlargement of 8 substations
Ziele
The refurbishing of the existing transmission lines aims at avoiding major power supply disruptions, and the new lines will extend the reach and quality of the transmission infrastructure in Benin and Togo. This will improve the reliability and efficiency of electricity supply, creating a better environment for private sector investment and growth.
Sektor(en)
Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)
Up to EUR 35 million
Gesamtkosten (voraussichtlicher Betrag)
EUR 73 million
Umweltaspekte
The Bank will verify that the impact of the project is in line with the EU and the Bank’s principles and standards as regards environmental and social issues.
Auftragsvergabe
All major contracts will be procured through international competitive bidding and the contracts financed by the Bank will be tendered in accordance with the EIB’s Guide to Procurement.
Projektstatus
Unterzeichnet - 22/12/2009