Referenz: 20030448
Veröffentlichungsdatum: 9 Januar 2004

Projektträger – zwischengeschaltetes Finanzinstitut

Electricity Authority of Cyprus (EAC).

Ort

Beschreibung

The project concerns the construction (turnkey Engineering, Procurement, Construction (EPC) contract) of a new CCGT generator (Unit 4) at the Vasilikos Power Plant, with a generating capacity in the range of 170 to 220 MW. The selection of the CCGT technology is largely explained by the assumed timely availability of natural gas on the island. The CCGT will operate on distillate oil for about 3 years and then switch to gas as primary fuel when Liquefied Natural Gas (LNG) will be available at the site.

Ziele

The project aims at the cost-effective supply of electricity, both to meet growing demand and to replace obsolete and less efficient existing generating capacity. Generally, an adequate and reliable provision of electricity at reasonable cost supports the economic development of Cyprus. Furthermore, the CCGT technology will raise the average thermal efficiency of the system and will contribute to minimise emissions of greenhouse gases and air pollutants per unit of electricity generated. The unit production cost and the environmental benefits should further improve once the initial use of gasoil can be replaced by natural gas.

Kommentar(e)

Electricity generation.

Sektor(en)

Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

Up to EUR 100 m.

Gesamtkosten (voraussichtlicher Betrag)

Of the order of EUR 160 m.

Umweltaspekte

Due to its size, the project falls under Annex I of Directive 97/11/EC and thus requires an Environmental Impact Assessment (EIA). Cyprus already applies the EU legislation on EIA and the project is expected to comply with EU policy and legislation in the field of environment. The appraisal will include the confirmation that there shall not be a negative impact on any important site of nature conservation. The project represents a more energy-efficient and low-emission technology than previously used in Cyprus. The project will also facilitate the decommissioning of old, inefficient and polluting heavy fuel oil power station units.

Auftragsvergabe

The project will have to comply with EU directives relevant to the sector, including publication in the Official Journal of the EC when appropriate.

Projektstatus

Unterzeichnet - 7/05/2004

Haftungsausschluss

Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).