Suche starten De menü ClientConnect
Suche starten
Ergebnisse
Top-5-Suchergebnisse Alle Ergebnisse anzeigen Erweiterte Suche
Häufigste Suchbegriffe
Meistbesuchte Seiten
Referenz: 20230350
Veröffentlichungsdatum: 17 September 2023

Projektträger – zwischengeschaltetes Finanzinstitut

JOHN COCKERILL HYDROGEN SAS,JOHN COCKERILL SA

Ort

Beschreibung

The project concerns corporate research and development (RDI) in the field of hydrogen technology and renewable energy, as well as new production capacity for a new generation of alkaline electrolysers for the production of green hydrogen. This will cover research and development related to the improvement of the alkaline electrolyser technologies and industrialisation of their advanced manufacturing process. The first manufacturing facility will be built across two locations in France and Belgium during 2023.

Ziele

The aim is to contribute to develop EU-based hydrogen industry, for which it can be considered an enabler. The project caters for the transition to a hydrogen economy, thereby supporting the competitiveness and climate ambitions of the EU heavy industry. Due to its enabling character for the transition to a hydrogen economy, the project fully contributes to Climate Action (mitigation) objective. It meets the objectives of the Green Deal Industrial Plan proposed by the European Commission.

Sektor(en)

  • Industrie - Verarbeitendes Gewerbe/Herstellung von Waren

Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

EUR 100 million

Gesamtkosten (voraussichtlicher Betrag)

EUR 214 million

Umweltaspekte

As the project concerns extensions to existing industrial plants, the project does not fall under Annex II of the EIA Directive 2014/52/EU amending Directive 2011/92/EU as amended by Directive 2014/52/EU and an environmental impact assessment (EIA) process is therefore subject to a screening decision of the Competent Authority. RDI activities are not covered by said Directive. The production facilities in Aspach, France has been screened in, with an EIA produced, and the environmental permit has gained legal force. The facilities in Seraing, Belgium are located within the physical boundaries of an existing plant and therefore screened out. Where and if applicable, the requirements of the EIA Directive 2011/92/EU as amended by Directive 2014/52/EU, Birds Directive 2009/147/EC and Habitats Directive 92/43/EEC (to be completed as relevant/applicable) and the requirements of social standards will be verified during appraisal. The Industrial Emissions Directive 2010/75/EU applies.

Auftragsvergabe

The promoter has been assessed by the EIB as being a private company not being subject to EU rules on public procurement or concessions. However, if the EIB were to conclude at project appraisal that the promoter is subject to the EU public procurement legislation, then the Bank would duly inform the Commission Services and would require the promoter to apply those rules.

Projektstatus

In Prüfung - 24/07/2023

Milestone
In Prüfung

Haftungsausschluss

Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

Tags

Frankreich Belgien Industrie