    Referenz: 20160729
    Veröffentlichungsdatum: 6 Februar 2017

    Projektträger – zwischengeschaltetes Finanzinstitut

    GE Financial Services / Macquarie Capital (Europe) Limited

    Ort

    Beschreibung

    The project comprises the construction of an onshore wind farm with a capacity of up to 650MW in northern Sweden about 25 km from the city of Piteå.

    Ziele

    The development of wind energy supports EU and national targets for renewable energy generation, and contributes to security of energy supply and environmental objectives.

    Sektor(en)

    Vorgeschlagene EIB-Finanzierung (voraussichtlicher Betrag)

    EUR 179 million

    Gesamtkosten (voraussichtlicher Betrag)

    EUR 741 million

    Umweltaspekte

    The Swedish government issued a framework permit for the Markbygden cluster in March 2010 based on an overarching environmental impact assessment (EIA) from 2008, covering the cumulative effects of the whole development. The complementary EIA for Phase 1, which includes this project, was issued in May 2011 and the competent authority issued the environmental permit in December 2011. The site is currently mostly used for industry related to forestry and reindeer husbandry. The potential impact on reindeer husbandry has been subject to special attention and consideration during the development phase of the project. The project will pay direct compensation to the neighbouring community and the Sami indigenous tribe, with whom an agreement on benefit-sharing has been reached based on free prior informed consent. During appraisal, compliance with the Bank's environmental and social standards will be assessed.

    Auftragsvergabe

    The promoter has been assessed by the EIB as being a private company not subject to EU rules on public procurement.

    Projektstatus

    Unterzeichnet - 7/11/2017

    Haftungsausschluss

    Bis Finanzierungen vom Verwaltungsrat genehmigt und anschließend unterzeichnet werden, befinden sich die Projekte in der Prüfungs- oder Verhandlungsphase. Die Angaben auf dieser Seite sind daher unverbindlich.
    Sie dienen lediglich der Transparenz und stellen nicht die offizielle EIB-Politik dar (vgl. auch die erklärenden Anmerkungen).

    Tags

    Schweden Energie